Client: Silverado Power
Location: Multiple States, USA
POWER Engineers provided engineering to support a series of Large Generator Interconnection Request (LGIR) applications to grid operators in four states, totaling in excess of 1,000 MW on 16 photovoltaic sites. POWER Engineers completed the engineering required to prepare applications and produced one-line diagrams and preliminary site layout design. POWER Engineers provided PVSyst generation modeling for ten sites located in various states.